Project organisation

Project New Sjölunda's organisation

Now that the procurement of the large and important collaboration contract is completed, the Nya Sjölunda project continue to work with two parts – a production preparation part and a technical part. The goal is to prepare, where possible, to optimize the start-up of the joint venture.

With the goal of a new Sjölunda wastewater treatment plant being completed by 2035, the project is working for a quick start when the main contractor for the joint venture is in place. This involves production preparations such as developing a time plan, analysing buildability and planning the construction phase, but also technical parts such as design, design preparations as well as requirements and scope work. In addition, work is underway on routines for the work environment and environment, as well as supporting documents for the ongoing permit process with the goal of obtaining a new environmental permit in 2027.

Project management

A organisation has been established, and the project's strategy and implementation roadmap are taking shape. In May 2025, Kristina Olofsson joined as project manager, and Magnus Jakobsson transitioned to the role as production manager for the project.

Kristina Olofsson

Kristina Olofsson, project manager New Sjölunda

Kristina brings more than 20 years of experience in project management into the Nya Sjölunda project. Most recently from 10 years at Region Skåne and Regionfastigheter as responsible for the new care building at Malmö hospital area. She also has many years of experience in construction projects in, among other things, the higher education and university sectors.

Magnus Jakobsson

Magnus Jakobsson, production manager New Sjölunda

Magnus has worked with MAXIMA and the Nya Sjölunda project for two years. He joined the programme organisation after just over 10 years at ESS, the new research facility in Lund. Magnus has over 20 years of experience as an entrepreneur, including from the projects Öresund Link and the City Tunnel.

Sub-project managers drive the preparations work

In the feasibility study for the New Sjölunda project, 15 sub-projects have been identified, to be further developed and confirmed with the coming main contractor. A number of sub-project managers in the client organisation are already working on preparations for selected parts of the facility. Some parts of the facility are critical for various reasons and need to start early in the contract, now being designed to the system document level.

De 15 delprojekten som ingår i projekt Nya Sjölunda illustreras i en work breakdown structure (WBS) för projekt Nya Sjölunda.

Work breakdown structure (WBS) for project New Sjölunda with the 15 sub-projects (in Swedish).