Tunnels and shafts – 1 procurement of 2 contracts
The construction of tunnels and shafts will be carried out in two contracts – one for E70 Northern wastewater tunnel and one for E80 Southern wastewater tunnel. The works will be procured as a single package, in which tenderers may choose to submit bids for one or both contracts. The most advantageous combination will be awarded.
Following solid planning, dialogue with the industry, and a decision on full financing, the procurement of the two tunnel projects for the MAXIMA wastewater system is now being launched. The plan is for construction works to begin in 2028 and be completed around 2032.
─ We are looking for the contractor or contractors best suited to deliver these projects, in close collaboration with the client organisation. It is important to us that the contracts are designed to be mutually beneficial and balanced from a risk perspective. In this way, we create strong conditions for efficient execution with high quality, says Stefan Milotti, Deputy Project Director for the Tunnel project.
Procurement process for Tunnels and shafts
The Tunnels and shafts procurement is a combinatorial procurement covering both contracts: E70 Norhtern wastewater tunnel and E80 Southern wastewater tunnel. The procedure will be conducted as a negotiated procedure with prior publication. A negotiated procedure means the procurement is carried out in two stages, where contractors first apply to be prequalified for tendering.
Contractors who are prequalified will be invited to submit bids, which may cover one or both contracts. The procurement form is a design-build contract, meaning that VA SYD is seeking a main contractor for each contract.
Contractors submitting bids for both contracts, and who consider it advantageous, will be given the opportunity to offer a discount, which will be taken into account in the tender evaluation. The discount will apply provided that the bidder is awarded both contracts.
VA SYD considers that there may be coordination advantages if a single contractor is responsible for both contracts. This will also be taken into account in the evaluation.
The final award may therefore be made either to two different contractors or to a single contractor for both E70 Northern wastewater tunnel and E80 Southern wastewater tunnel, depending on which option is deemed overall the most economically advantageous for VA SYD.
Procurement timeline
Summer 2026 – publication of prequalification invitation
End of 2026 – publication of the tender documents to qualified contractors
Read more about the scope for the northern wastewater tunnel here
Read more about the scope for the southern wastewater tunnel here