A number of contracts in the scope of the Tunnel project
The Tunnel project comprises the construction of the parts required for the transport and pumping of wastewater to Sjölunda wastewater treatment plant (WWTP). This is divided into a number of contracts, which will be procured at different times.
The Tunnel project is responsible for the transport, storage, and pumping of wastewater to the Sjölunda WWTP, including functions according to the following scope:
- The Northern wastewater tunnel: a 10.5 kilometres long tunnel, with an internal diameter of 3 metres, located between Källby in Lund and the Sjölunda pumping station in Malmö.
- The Southern wastewater tunnel: a 5.5 kilometres long tunnel, with an internal diameter of 5 metres, located between the central parts of Malmö and the Sjölunda pumping station, and two micro tunnels with a total length of 2.4 kilometres and an internal diameter of 2 metres.
- Sjölunda pumping station: a new pumping station located next to the Sjölunda WWTP, connecting the wastewater tunnels with the treatment plant.
- Transfer pipes from Borgeby: a new pressurised pipe system for transporting the wastewater from Borgeby in the municipality of Lomma to the Northern wastewater tunnel.
─ The project is technically challenging and in some parts complex. Therefore, we want to find contractors with extensive experience from projects of the same nature, scope and complexity, says Stefan Milotti, Project Manager for the Tunnel project
The division is based on key factors
In dividing the contracts, the project has primarily taken into account interfaces, construction methods, and execution timelines, as well as external analysis and comparisons with projects of a similar nature. The programme’s overall procurement strategies form the planning framework for the project’s contract procurements.
The tunneling works will be procured as turnkey contracts, with the general contractor entering once the basic system design has been completed. The payment model will be unit price contract. For the other contracts, this has not yet been decided.
Read more about the different contracts – Tunnels and shafts, Groundworks, Sjölunda pumping station, and Transfer pipe Borgeby – below.
Current activities
- Basic design of the wastewater tunnels and shafts
- Conclusions are drawn from the market dialogue, in the form of a Request for Information (RFI) for the tunnel contracts, which was carried out during spring 2025
- Preparations for the prequalification of potential contractors for the subproject Tunnels and shafts, planned for spring 2026
- Project Automation published a Request for Information (RFI) in mid-September 2025
- Strengthening the project organisation with necessary competences