Application for an environmental permit
To enable construction of the MAXIMA wastewater treatment system to begin, VA SYD must apply for and obtain permits in accordance with Chapters 9 and 11 of the Environmental Code. This is an extensive process that includes several steps. A public referral period is currently underway, during which anyone may submit their views to the Land and Environment Court.
VA SYD’s application for an environmental permit for MAXIMA comprises about 3,000 pages and is the result of several years of thorough preliminary studies, including a new consultation process and investigations carried out in collaboration with experts in various fields. The application was submitted to the Land and Environment Court in Växjö in May 2025. In order for the case to proceed to review, the court requested additional information, which was submitted in early March 2026.
The court has now assessed the application as complete and announced this in the local press on 16 April, 2026. This marked the start of the court’s referral period, during which anyone may submit comments to the court. The referral period is expected to continue until the turn of May/June. After that, work will begin on addressing the submitted comments, and those who have provided input will be given the opportunity to review the responses. The court will then announce when a main hearing can take place.
VA SYD estimates that a main hearing could be held in early 2027, and that a decision on the environmental permit may be issued in late spring/early summer 2027, which would allow construction to begin.
Scope of the permit application
In short, VA SYD is applying for an environmental permit for this:
To obtain a permit with conditions for the discharge of treated wastewater from 820,000 population equivalent (a measure for the design of wastewater treatment plants) from a new Sjölunda wastewater treatment plant
To build a robust new Sjölunda wastewater treatment plant with new outfall pipelines into the Öresund, a new pumping station at Sjölunda, a wastewater tunnel under Malmö and a wastewater tunnel from Lund
Discharge of groundwater, infiltration and other water activities such as works in the Öresund during the construction phase
Any permit required to operate in or near Natura 2000 sites.
About the judicial proceedings
Permit decision
The permit application under the Continental Shelf Act that was submitted to the Government in 2023 remains in place and is currently dormant. VA SYD is working to ensure that permits under both the Environmental Code and the Continental Shelf Act are obtained simultaneously.