Flygfoto över Sjölunda avloppsreningsverk taget från strandkanten in mot land.
MAXIMA

The new Sjölunda wastewater treatment plant

Expansion and remodeling of the Sjölunda wastewater treatment plant

The new Sjölunda wastewater treatment plant with a new treatment process will be built on the same site as the current wastewater treatment plant while it is in full operation. To be successful, the work must be carried out in stages with major temporary diversions. 

Scope
Time: the work is divided into two phases. Phase 1, design planning, is estimated to take 1,5-2 years and phase 2, production, is estimated to take around 8 years 
Treatment capacity: 820 000 personal equivalents
Maximum flow: 10 m3/s
Area: 600x350 metres
New buildings: around 20, totalling 30 000 m2
New basins outdoors: 40 000 m2
Pipelines: approximately 10 000 m
Concrete: approximately 60 000 m3
Excavation: 180 000 m3

The Nya Sjölunda project

Sjölunda wastewater treatment plan - the hub of the regional wastewater treatment system MAXIMA

Magnus Jakobsson, acting project manager, and Eric Goddard, project engineer, talks about the the Nya Sjölunda project, the challenges with the expansion and remodeling of the wastewater treatment plant, and the planned partnering contract.

Implementation plan

It is complex and challenging to build the new wastewater treatment plant on the same site while the current plant is in operation, as the construction and process installation must be carried out in stages with major temporary diversions. How the work will be carried out is described in a implementation plan. We have visualised the development plan in a slideshow. 

Potential technological developments may lead to changes and new requirements in the course of the work.

The new wastewater treatment process

Water treatment line

When the wastewater reaches the new wastewater treatment plant via the inflow pumping station, it first passes through screens that capture larger particles. Sand and gravel are then separated in sand traps before the wastewater passes to pre-sedimentation tanks where higher density particles sink to the bottom of the tank and form a sludge. The wastewater is then passed on to a biological process, the membrane bioreactor (MBR). There, the treated water is separated from the sludge by membranes with very small pores that allow only the treated wastewater to pass through. The wastewater then reaches the outflow pumping station. Most of the water treatment line will be new or reconstructed. Screens and sand traps are retained.  

The water treatment line will also consist of high flow treatment to be used when flows are high.  

Sludge treatment

The water treatment line produces sludge which is pumped to the sludge treatment plant. Sludge treatment will consist of mechanical thickening, pasteurisation, digestion and sludge dewatering. These plants components will be constructed or reconstructed. 

Flygbild Sjölunda avloppsreningsverk tagen från strandkanten in mot land

An aerial photo of the current Sjölunda wastewater treatment plant.

Flygbild över Sjölunda avloppsreningsverk med rutor som markerar var de nya anläggningsdelarna är planerade

An overview of the planned layout for the new wastewater treatment plant (in Swedish).

Illustration som illustrerar vilka anläggningar som ska rivas och behållas på Sjölunda avloppsreningsverk

The demolition plan for Sjölunda wastewater treatment plant (in Swedish).

What is happening right now

  • The plan for the project is to send out documents for the qualification of tenderers during Q4 2024. We will present a more detailed time plan for the procurement during the fall.